Educational worked example · sample inputs
A cheap rate with heavy curtailment
$0.0653/kWh effective, 45% above advertised
Illustrative inputs
| Term | Value |
|---|---|
| Advertised power rate | $0.045 / kWh |
| Management fee | 5% of power |
| Power factor uplift | 3% |
| Unplanned downtime | 4% of hours |
| Curtailment | 20% of hours |
| Pool fee | 2% of revenue |
The working
| Step | Result |
|---|---|
| Advertised rate | $0.0450 |
| Plus fees (8%) | $0.0486 |
| Effective uptime after 24% lost hours | 76.0% |
| Cost per productive kWh | $0.0639 |
| Equivalent pool-fee adjustment: divide by 0.98 | $0.0653 |
Educational inputs, not a quoted offer. A $0.045 rate with 8% combined added fees gives $0.0486/kWh. With 4% downtime and 20% separate curtailment, the productive-hours fraction is 0.76.
Dividing $0.0486 by 0.76 and then 0.98 gives an equivalent $0.0653 per productive kWh, approximately 45% above the sample rate. This assumes booked capacity stays payable during lost hours and represents pool fees as a comparison adjustment.
Compare offers on absolute equivalent cost under the same billing assumptions. The percentage uplift alone cannot rank providers or establish profitability.
Run it with your own numbers
Load these inputs in the calculator and change any input. The URL includes the assumptions for this example. Sharing it exposes those inputs; it sends no order or contract amount.
Not sure which number goes where? What your hosting contract costs per productive kWh covers every setting and where to find yours.
Last reviewed . Figures marked illustrative are placeholders, not live data.